NEW QUESTION # 59
You have concluded a cleaning contract with a supplier for your operating facility. You aQreed on a monthly amount for which you want to automatically create a credit note every month. What do you usein this scenario?

  • A. Blanket purchase order
  • B. Scheduling agreement
  • C. Invoicing plan
  • D. Value contract

Answer: C

Explanation:
Explanation
You use an invoicing plan in this scenario. An invoicing plan is a method of creating invoicesautomatically at predefined intervals or dates without referring to any service entry sheets or goods receipts. You can use an invoicing plan for blanket purchase orders or contracts that have a fixed amount and validity period.
References: [SAP S/4HANA Sourcing and Procurement | SAP Learning], Course S4520, Unit 2, Lesson 1.


NEW QUESTION # 60
What is one difference between the SAP Fiori launchpad and the classical SAP Graphical User Interface (SAP GUI)?

  • A. The SAP Fiori launchpad enables browser-based transactions, while SAP GUI does NOT.
  • B. The SAP Fiori launchpad provides maintenance of favorites and file access, while SAP GUI ^ only provides maintenance of favorites.
  • C. The SAP Fiori launchpad can be personalized, while SAP GUI CANNOT be personalized.
  • D. The SAP Fiori launchpad is role-based, while SAP GUI often offers single complex transactions for many user roles.

Answer: D


NEW QUESTION # 61
At which of the following organizational levels must you maintain a business partner master record for a supplier? Note: There are 3 correct answers to this question.

  • A. Client
  • B. Company code
  • C. Purchasing group
  • D. Plant
  • E. Purchasing organization

Answer: A,B,E

Explanation:
Explanation
A business partner master record for a supplier is a central data record that contains information about the general data, accounting data, and purchasing data for a supplier. You must maintain a business partner master record for a supplier at the following organizational levels:
Client, which is the highest level in the SAP system hierarchy and contains data that is valid for all organizational units.
Purchasing organization, which is an organizational unit that is responsible for procuring materials or services for one or more plants and negotiating prices and conditions with vendors.
Company code, which is the smallest organizational unit for which a complete self-contained set of accounts can be drawn up. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4500, Unit 1, Lesson 1.


NEW QUESTION # 62
There are multiple company codes and plants in your SAP S/4HANA system.You have set the valuation area to plant level. How can you reduce the effort to configure account determination?

  • A. You can use the account grouping code to group together plants assigned to company codes with different charts of accounts.
  • B. You can use the account grouping code to group together plants assigned to company codes with the same chart of accounts.
  • C. You can use the valuation grouping code to group together plants assigned to company codes with the same chart of accounts.
  • D. You can use the valuation grouping code to group together plants assigned to company codes with different charts of accounts.

Answer: C

Explanation:
Explanation
You can use the valuation grouping code to group together plants assigned to company codes with the same chart of accounts. This reduces the effort to configure account determination because you only need to maintain one set of valuation classes and account assignments for each valuation grouping code instead of each plant. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4550, Unit 1, Lesson 1.


NEW QUESTION # 63
You want to create a purchase order. An info record is available for the material-supplier combination. What logic does the system use to determine a price from the info record? Note: There are 2 correct answers to this question

  • A. The system always proposes the valid plant-specific price, if available.
  • B. The system always proposes the price from the last purchase order, if available.
  • C. The system always proposes the price stored at purchasing organization level, if available.
  • D. If there are NO valid conditions, the system can propose the price from the last purchase order, if available.

Answer: A,D


NEW QUESTION # 64
Which field in the material type controls whether a material is used in the lean service process?

  • A. Product Type Group
  • B. Item Category Group
  • C. Field Reference
  • D. External Purchase Orders

Answer: A


NEW QUESTION # 65
Where does SAP S/4HANA store low-level code? Note:There are 2 correct answers to this question.

  • A. Bill of material
  • B. Production version
  • C. Material Master
  • D. Planning file

Answer: B,C


NEW QUESTION # 66
In your company, you are posting an invoice with a cash discount amount using the posting gross method.
What is the result of this in the system?

  • A. The cash discount amount is NOT considered; it is only posted to a cash discount account when the payment is made.
  • B. The cash discount amount is posted to a cash discount clearing account, which is cleared at ^ the time of payment.
  • C. The cash discount amount is credited to the stock or cost account.
  • D. The cash discount amount is posted from a cash discount clearing account to the stock account or cost account.

Answer: B

Explanation:
Explanation
When posting an invoice with a cash discount amount using the posting gross method, the cash discount amount is posted to a cash discount clearing account, which is cleared at the time of payment. The posting gross method means that the invoice amount is posted in full to the vendor account and the cash discount clearing account, regardless of whether the payment is made within the cash discount period or not.
References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4515, Unit 3, Lesson 1.


NEW QUESTION # 67
Which of the following activities is a prerequisite to enable partner role detarmraton m purchasing?

  • A. Define permissible partner roles per account group.
  • B. Define permissible partner roles per document type.
  • C. Assign a partner schema to relevant arrangement types.
  • D. Assign a partner schema to lelevanl account groups.

Answer: C

Explanation:
Explanation
To enable partner role determination in purchasing, you must assign a partner schema to relevant document types. A partner schema is a configuration that defines the possible partner roles and functions for a purchasing document such as purchase requisition, purchase order, contract, or scheduling agreement. You can assign a partner schema to a document type in Customizing under Materials Management -> Purchasing -> Partner Determination -> Assign Partner Schemas to Document Types. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4520, Unit 3, Lesson 2.


NEW QUESTION # 68
Which of the following procurement proposals can be created during an MRP Live planning externally procured materials? Note: There are 2 correct answers to this question.

  • A. Delivery schedule line
  • B. Purchase requisition
  • C. Planned order
  • D. Purchase order

Answer: A,B

Explanation:
Explanation
MRP Live is a planning run that is executed on SAP HANA database using optimized algorithms and parallel processing. It can create two types of procurement proposals for externally procured materials:
Delivery schedule line: This is a line item in a scheduling agreement that specifies the delivery date and quantity for a material.
Purchase requisition: This is an internal document that requests the purchasing department to procure a certain quantity of a material or service by a certain date. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4525, Unit 1, Lesson 1.


NEW QUESTION # 69
What are some advantages of a stock transport order compared to a stock transfer posting between two plants?
Note; There are 3 correct answers to this question.

  • A. You can post goods receipt to consumption.
  • B. You can create stock transport requisitions via MRP.
  • C. You can post goods receipt in consignment.
  • D. You can issue from inspection stock.
  • E. You can plan delivery costs.

Answer: A,B,E

Explanation:
Explanation
A stock transport order is a special type of purchase order that allows you to transfer stock between two plants.
Compared to a stock transfer posting, a stock transport order has some advantages, such as:
You can create stock transport requisitions via MRP, which means you can plan the stock transfer based on the demand and supply situation of the plants1.
You can post goods receipt to consumption, which means you can directly consume the transferred stock without updating the inventory2.
You can plan delivery costs, which means you can include the transportation costs in the valuation of the transferred stock. References: SAP Help Portal, SAP Community, [SAP Blogs]


NEW QUESTION # 70
Which of the following are features of a scheduling agreement? Note: There are 3 correct answersto this question.

  • A. A scheduling agreement item is always plant-specific .
  • B. A scheduling agreement can be used for a consignment process.
  • C. Item category M (Material unknown) can be used in a scheduling agreement.
  • D. A material master record is optional in a scheduling agreement item.
  • E. Scheduling agreement delivery schedule lines can only be created manually.

Answer: A,B,D

Explanation:
Explanation
A scheduling agreement is a long-term agreement with a vendor for the supply of materials or services according to a predefined delivery schedule. Some features of a scheduling agreement are:
A material master record is optional in a scheduling agreement item. You can use item category M (Material unknown) to enter a short text and material group instead of a material number.
A scheduling agreement can be used for a consignment process. You can use item category K (Consignment) to indicate that the materials are stored at your premises but are still owned by the vendor until you consume them.
A scheduling agreement item is always plant-specific. You must specify a plant for each scheduling agreement item and you cannot change it afterwards. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4520, Unit 5, Lesson 1.


NEW QUESTION # 71
How can you completely block a material for procurement in a plant? Note: There are 2 correct answers to this question.

  • A. Create a quota arrangement entry with a quantity of zero
  • B. Create a blocking entry in the supplier master record
  • C. Create an entry in the source list with a blocking indicator and NO supplier
  • D. Use a relevant plant-specific material status in the material master

Answer: C,D


NEW QUESTION # 72
For which documents can you configure the usage of time-dependent conditions? Note: There are 2 correct answers to this question.

  • A. Contract
  • B. Quotation
  • C. Purchase order
  • D. Scheduling agreement

Answer: B,D


NEW QUESTION # 73
Which situations lead to an open item on the GR/IR clearing account? Note: There are 2 correct answers to this question.

  • A. The invoiced quantity for a purchase order item is more than the delivered quantity.
  • B. The ordered quantity for a purchase order item is more than the delivered quantity.
  • C. The delivered quantity for a purchase order item is more than the invoiced quantity.
  • D. The ordered quantity for a purchase order item is more than the invoiced quantity.

Answer: A,C


NEW QUESTION # 74
Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.

  • A. Perform backward scheduling to determine the availability dates of purchase requisitions
  • B. Carry out a net requirement calculation for every material included in the planning run
  • C. Carry out a lot-size calculation for every material with net requirements
  • D. Flag materials that have been subject to an activity relevant to MRP

Answer: B,C


NEW QUESTION # 75
What can you create to plan materials differently within a plant?

  • A. Production supply areas
  • B. Vendor consignment info records
  • C. Storage bins
  • D. MRP areas

Answer: D


NEW QUESTION # 76
What are the prerequisites for carrying out material requirements planning (MRP) for a plant?
Note; There are 2 correct answers to this question.

  • A. Maintain MRP data in the material master record for the materials to be planned automatically.
  • B. Maintain planned independent requirements lot the materia s in the plant.
  • C. Assign each storage location of the corresponding plant to an MRP area in Customizing.
  • D. Maintain plant parameters for the corresponding plant in Customizing.

Answer: A,D

Explanation:
Explanation
Material requirements planning (MRP) is a process that calculates the net requirements and generates planned orders or purchase requisitions for materials based on various factors, such as demand, supply, lead time, lot size, safety stock, etc. To carry out MRP for a plant, some prerequisites are needed. Two of them are:
Maintain MRP data in the material master record for the materials to be planned automatically: This prerequisite is necessary, as the MRP data contains the parameters that control how the system plans the material, such as MRP type, MRP group, MRP controller, lot size, procurement type, special procurement, etc. Without these parameters, the system cannot determine the optimal quantity and timing of the material requirements.
Maintain plant parameters for the corresponding plant in Customizing: This prerequisite is necessary, as the plant parameters define the global settings that apply to all materials in the plant, such as planning horizon, planning calendar, opening period, scheduling margin key, etc. These settings influence how the system calculates the dates and quantities of the planned orders or purchase requisitions.


NEW QUESTION # 77
What is one difference between the SAP Fiori launchpad and the classical SAP Graphical User Interface (SAP GUI)?

  • A. The SAP Fiori launchpad enables browser-based transactions, while SAP GUI does NOT.
  • B. The SAP Fiori launchpad provides maintenance of favorites and file access, while SAP GUI ^ only provides maintenance of favorites.
  • C. The SAP Fiori launchpad can be personalized, while SAP GUI CANNOT be personalized.
  • D. The SAP Fiori launchpad is role-based, while SAP GUI often offers single complex transactions for many user roles.

Answer: D

Explanation:
Explanation
One difference between the SAP Fiori launchpad and the classical SAP Graphical User Interface (SAP GUI) is that the SAP Fiori launchpad is role-based, while SAP GUI often offers single complex transactions for many user roles. This means that the SAP Fiori launchpad provides a user-friendly and personalized access to the applications and tasks that are relevant for a specific user role, while SAP GUI often requires users to navigate through menus and screens that are not relevant for their role. References: [SAP S/4HANA Sourcing and Procurement | SAP Learning], Course S4500, Unit 1, Lesson 1.


NEW QUESTION # 78
Which of the following apply when using centrally agreed contracts? Note; There are 2 correct answers to this question.

  • A. You CANNOT specify plants in centrally agreed contracts.
  • B. You can use centrally agreed contracts in a procurement hub scenario.
  • C. You can use centrally agreed contracts without restrictions for any purchasing organization.
  • D. You can maintain plant-specific conditions in centrally agreed contracts

Answer: A,B

Explanation:
Explanation
Centrally agreed contracts are contracts that are created by a central purchasing organization and can be used by multiple purchasing organizations within a company. Some of the characteristics of centrally agreed contracts are:
You can use centrally agreed contracts in a procurement hub scenario, which means that you can leverage the central purchasing organization's negotiation power and expertise to procure materials or services for other purchasing organizations.
You cannot specify plants in centrally agreed contracts, which means that the contracts are not plant-specific and can be used by any plant that belongs to the purchasing organizations that are assigned to the central purchasing organization. References: [SAP Help Portal], [SAP Help Portal]


NEW QUESTION # 79
......

C_TS452_2022 Exam Dumps Contains FREE Real Quesions from the Actual Exam: https://dumpstorrent.exam4pdf.com/C_TS452_2022-dumps-torrent.html